Though in working condition, the radar system at Dhaka airport is way outdated compared to global standards. So the government has decided to install new radars soon on its own DHAKA TRIBUNE
The government has made a proposal to install radar at Hazrat Shahjalal International Airport using its own funds, instead of through a Public-Private Partnership (PPP) as had been previously considered.
Explaining that the previous PPP project would have led to exaggerated expenditure, SM Ghulam Farooque, secretary of the Civil Aviation and Tourism Ministry, mentioned that the new project would be more cost efficient.
The project, titled “Supply, Installation and Commissioning of a Multi Mode Surveillance System (Radar, ADS-B Wide area Multilateration -WAM) along with ATC and Communication system at Hazrat Shahjalal International Airport (HSIA), Dhaka”, will be placed at the Cabinet Committee on Public Purchase meeting which is scheduled to be held today.
In the project summary, Ghulam Farooque said: “In 2013, the Civil Aviation Authority, Bangladesh (CAAB) informed the Aviation ministry that it would cost Tk200 crore to install a radar system at Shahjalal International Airport. No government earnings would have been made under the project.”
He added that radar is an important part of ensuring security and safety in the sky, and the government should not implement this project under the PPP system for global security reasons. Moreover, the government would have had to repay Tk1,755 crore, excluding VAT, though the bidders project proposal was worth an exaggerated Tk579 crore.
Karim Associates fixed the bid price at Tk1700 crore, before CAAB finally sent the project to the Civil Aviation ministryEarlier, the Civil Aviation and Tourism ministry had asked CAAB to review the Radar project of Hazrat Shahjalal International Airport, worth Tk1,700 crore.
A meeting was held in November of last year to approve the project, but the PPP proposal was rejected by the ministry after close scrutiny of the predicted cost. Subsequently, the government decided to install the radar project independently, without the PPP.
Installation of the new radar system has top priority from CAAB, who wish to implement it by 2017 as part of its up-gradation of air traffic control and management to come in line with International Civil Aviation Organisation (ICAO) guidelines.The existing radar, set up in 1986, has long been obsolete and cannot manage air traffic properly, according to CAAB.
Among the problems with the current system is that it sometimes fails to detect air traffic uninterruptedly. It operates for only 12 hours a day and not at all on Saturdays, putting thousands of travelling passengers at risk.
Foreign airlines have not been using the country’s air navigation services since 2015, due to the systems at Shahjalal Airport being in breach of ICAO regulations.Initially, the Committee on Financial Affairs approved the Tk330 crore project in 2013, however, the project cost has since increased dramatically.
A total of 17 organizations participated in the pre-bid meeting, held in December 2015, with four organizations submitting tender proposals. To evaluate the tender proposals, CAAB formed a Qualification and Technical Evaluation committee, led by its chairman.Selected company Karim Associates fixed the bid price at Tk1700 crore, before CAAB finally sent the project to the Civil Aviation ministry.
Upon receiving approval from the ministry, the proposal would have been sent to the Cabinet Committee on Public Purchase, but the Aviation ministry sent back the project for further review as cost was too high.